July / August / September 2011
June 2011
May 2011
(black smoke for an initial short time only until the exhaust ducting is cleared of oil preservative).
April 2011
March 2011
The assembly of the pre-fabricated pipework modules is now completed and the cabling is installed along the cable trays. The build up of the bulk fuel storage tanks upon the foundations now accelerates.
February 2011
All major items of generating plant equipment are now in position. The assembly of the pre-fabricated pipework and cabling now begins which will link together all the separate modules.
January 2011
Progress continues on site with the installation of the largest components (gensets and chimney stacks) completed.